as soon as they could be delivered, the first on July
25th and the third on September 12th. The excavated
material was loaded by the shovels on end-dump wagons,
each having a capacity of 2 cu. yd., and was conveyed
in them to the dumping board at 35th Street. The
average number of teams was 135, 10% being snatch
teams to pull the wagons out of the pit and to assist
them up the runway at the dumping board. The teams
averaged only seven trips per day of 10 hours, considerable
delay being caused by the trains of the New York Central
Railroad at Eleventh Avenue. The number of teams
was not sufficient, therefore, to keep the three shovels
busy when they were all in good digging, but the dumping
board was taxed to accommodate that number, and little
would have been gained by increasing it. The
digging was very good during this period, practically
no rock being encountered, and the building foundations
were too light to present any obstacle to such powerful
shovels. The capacity of their dippers was 31/2
cu. yd., so that one dipperful meant one truck loaded
and running over. The output from August to November,
inclusive, averaged 40,000 cu. yd. per month; one
shift only was worked per day, and although the quantity
was not large for three such powerful shovels, it
was large to truck through the streets, and required
that one team pass a given point every 18 sec.
At the end of November the opening up of the pit had
been accomplished, considerable rock had been stripped
near Ninth Avenue, and the streets had become so icy
that the cost of transportation was practically doubled;
work in the pit, therefore, was much curtailed, and
amounted to continuous work for one shovel from that
time until the end of the period, May 22d, 1905, when
Pier No. 72 was put in service and transportation
by train began. Figs. 2 and 3, Plate LVI, show
the condition of the pit east and west of Eighth Avenue,
respectively, on that date.
[Illustration:
Fig. 9.
SKETCH SHOWING TYPICAL BENT OF TRESTLE
SUPPORTING EIGHTH AVENUE]
The work of excavating for and building the temporary
street bridge, a typical bent and bracing for which
are shown on Fig. 9, and the cast-iron sewer and water
mains in Eighth Avenue, was commenced on September
3d, 1904. The trestle was a double-decked structure
of yellow pine, with 10 by 10-in. posts and sills,
10 by 14-in. intermediate and top caps, and 2 by 10-in.
longitudinal and cross-braces. The trestle was
further stiffened longitudinally by four lines of 8
by 10-in. struts, butted between the intermediate
caps, and held in position by 2 by 8-in. splice-plates
resting on top of them. The intermediate caps
were at an elevation of 15 ft. below the surface of
the street, and above that line the longitudinal bracing
was continuous, while below it the bents were braced
in pairs, the bracing being omitted from every second
bay. Below the intermediate cap the bents were
uniform for the entire width of the trestle, but the
top cap was not continuous, being 5 ft. below the
surface under the trolley tracks, and only 18 in.,
the depth of stringers and planking, beyond.
The stringers under the trolley tracks were 8 by 16-in.
yellow pine, spaced three to a track, and those for
the driveway were 6 by 14-in., spaced 1 ft. 6 in.
on centers, the planking being 4-in. yellow pine.